Tamarisk Corp. enters into a contract with a customer to build an apartment building for $930,000. The customer hopes to rent apartments at the beginning of the school
year and provides a performance bonus of $151,500 to be paid if the building is ready for rental beginning August 1, 2018. The bonus is reduced by $50,500 each week
that completion is delayed. Tamarisk commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion
outcomes: Completed by Probability August 1, 2018 70 % August 8, 2018 20 August 15, 2018 5 After August 15, 2018 5 Determine the transaction
price for this contract. Transaction Price $