A project to remodel a garage has the following activities
Subject: General Questions / General General Questions
Question
ar.tamanna
Question:
Please reply me with solutions and calculations as soon as possible. I have 45 minutes
(TCO C) A project to remodel a garage has the following activities. (Hint: You will need to build an AIB/AON diagram, perform a forward pass, and perform a backward pass to answer this question.)
ActivityDurationPredecessors
A4 months—
B3 months—
C3 months—
D5 monthsC
E3 monthsA, B
F3 monthsB, C
G3 monthsE, F
H4 monthsD, F
I5 monthsG
J2 monthsH
What are the critical path activities? (8 points)
What is the project's scheduled completion time? (8 points)
What is the slack or float for Activity C? Show your calculations. (8 points)
What is the slack or float for Activity D? Show your calculations. (8 points)
What is the slack or float for Activity F? Show your calculations. (8 points)
(Points : 40)
(TCO A) In the _____ organization structure, the project manager is responsible for the project results. He or she controls all the project resources and employs cross-functional teams to accomplish the project.
Weak Matrix
Strong Matrix
Pure Project
Functional
(TCO A) The project plan is executed in the _____. (Points : 10)
initiating phase
planning phase
executing phase
closing phase
TCO F) It is important to use the _____ as the standard against which actual cost is compared. (Points : 10)
cumulative budget
total budget
budget at completion
phased budget
TCO H) A project audit provides an opportunity to evaluate issues and concerns to determine potential improvements. A project audit should contain the following information. (Points : 10)
Project charter, scope, and assumptions
Risk assessment, future projections, and audit limitations
Resource skills and assignments
Communications management plan