Project Management MCQs Assignment

Project Management MCQs Assignment

Multiple Choice: ( select the most correct response )
1. Average job completion time is:
a.
b.
c.
d.

total processing time divided by the number of jobs.
total flow time divided by the number of jobs
total flow time divided by total processing time.
total flow time minus total late time.

2. Work center loading:
a. is done prior to detailed scheduling.
b. does not incorporate a priority sequence rule.
c. is the assignment and commitment of specific jobs to each work center for the
planning period.
d. all of the above.
3. When using the critical ratio ( CR ) priority sequence rule:
a. a ratio of less than 1.0 implies that a job has a priority over a job with a ratio of
more than 1.0.
b. a ratio of more than 1.0 implies that a job has priority over a job with a ratio of
less than 1.0.
c. the job with the earliest due date is scheduled first.
d. none of the above.
4. Which of the following is not a performance measure used in scheduling?
a.
b.
c.
d.

job flow time.
tardiness.
labor capacity requirements.
utilization.

5. Gantt charts have several major limitations to include:
a. the need to be updated regularly to account for new job arrivals and revised time
estimates.
b. the inability to assess the relative work loads at each work center.
c. the inability to serve as a foundation for the detailed scheduling function.
d. the inability to signal the need for reallocation of labor and equipment to busier
work centers.

6. Assume a task has the following times: a = 10, m = 25, and b = 40. Its expected time is:
a.
b.
c.
d.
e.

10
25
40
30
none of the above.

7. The critical path of a network is the:
a.
b.
c.
d.
e.

shortest time path through the network.
path with the fewest activities.
path with the most activities.
longest time path through the network.
none of the above.

8. Given the following activitys optimistic, most likely, and pessimistic time estimates of 2, 10, and 20 days respectively, compute the PERT variance for this
activity:
a.
b.
c.
d.
e.

3
6
9
18
none of the above.

9. Managers use the network analysis of PERT and CPM to help them:
a.
b.
c.
d.

derive flexibility by identifying noncritical activities.
replan, reschedule, and reallocate resources such as manpower and finances.
plan, schedule, monitor, and control large and complex projects.
all of the above.

10. In an activity-on-node (AON) network, the nodes represent______whereas
the arcs represent _________.
a.
b.
c.
d.

activities; time
activities; precedence relationships
events; activities
precedence relationships; time

True or False: ( select the one correct response )

11. A job shop is a firm that specializes in medium- to large-volume production
and utilizes line or continuous processes.
TRUE

FALSE

12. The gantt chart ( for loading ) shows the order in which each job will be processed at each work center.
TRUE

FALSE

13. Earliest due date ( EDD ) is a priority sequencing rule that states the job requiring the shortest processing time is the next job to be processed.
TRUE

FALSE

14. Dispatching is the assignment and commitment of incoming jobs to one or
more specific work centers, for the day or week.
TRUE

FALSE

15. The DDATE priority sequence rule will always minimize average job lateness.
TRUE

FALSE

16. The gantt chart ( for loading ) provides the basis for the promised date of the
job to the customer.
TRUE

FALSE

17. The assignment algorithm is an alternative method for performing the loading function in a job shop.
TRUE

FALSE

18. The gantt chart ( for supplementary scheduling ) allows management to
monitor the progress of all jobs in the system in real time.
TRUE

FALSE

19. Activities on the critical path exhibit positive slack times.
TRUE

FALSE

20. The variance of project completion time equals the variances of all activities
in the project.
TRUE

FALSE

21. The expected activity time is the average of an activitys optimistic and pessi
-mistic times.
TRUE

FALSE

22. Dummy activities are found in activity-on-arc (AOA) convention PERT/
CPM network models.
TRUE

FALSE

23. The dummy activity has an expected time of zero by definition.
TRUE

FALSE

24. Early start time ( ES ) is computed from right to left ( backward pass ).
TRUE

FALSE

25. The project-group approach extends little or no formal authority to the
project coordinator.
TRUE

FALSE

PRACTICAL PROBLEMS
26. In problem one, the static slack for job E is:
a.
b.
c.
d.
e.

3
4
5
6
none of the above.

27. In problem one, the static slack for job F is:
a.
b.
c.
d.
e.

16
15
14
13
none of the above.

28. In problem one, the lateness for job C is:
a.
b.
c.
d.
e.

0 days
1 day
2 days
5 days
none of the above.

29. In problem one, the average job completion time is:
a. 12 days
b. 13 days
c. 14 days
d. 15 days
e. none of the above.
-230. In problem one, the average job lateness is:
a.
b.
c.
d.
e.

2.666 days
3.666 days
4.666 days
5.666 days
none of the above.

31. In problem one, the number of late jobs will be:
a.
b.
c.
d.
e.

2
3
4
5
none of the above.

32. In problem two, the critical path is:
a.
b.
c.
d.
e.

13 weeks
16 weeks
19 weeks
22 weeks
none of the above.

33. In problem two, the early finish ( EF ) time for activity H is:
a.
b.
c.
d.
e.

7th week
8th week
9th week
10th week
none of the above.

34. In problem two, the early start ( ES ) time for activity F is:
a.
b.
c.
d.
e.

5th week
6th week
7th week
8th week
none of the above.
-3-

35. In problem two, the late start ( LS ) time for activity H is:
a.
b.
c.
d.
e.

16th week
17th week
18th week
19th week
none of the above.

36. In problem two, the late finish ( LF ) time for activity F is:
a.
b.
c.
d.
e.

16th week
17th week
18th week
19th week
none of the above.

37. In problem two, the slack time ( S ) for activity D is:
a.
b.
c.
d.
e.

0 weeks
1 week
2 weeks
3 weeks
4 weeks

38. In problem three, car 3 will be assigned to:
a.
b.
c.
d.

Bob
Fred
Mike
Tim

39. In problem three, car 1 will be assigned to:
a.
b.
c.
d.

Bob
Fred
Mike
Tim
-4-

40. In problem three, the total number of labor hours required will be:
a.
b.
c.
d.
e.

30 hours
35 hours
40 hours
45 hours
none of the above.