Accounts receivableconstruction contract billings $18,000Â
Construction in process $65,000 Less: Contract billings 61,500Â
Cost of uncompleted contract in excess of billings 3,500
 Income Statement Income (before tax) on the contract recognized in 2012 $19,500 2012 2013 2014
 Costs incurred to date $280,000 $600,000 $ 785,000 Estimated costs yet to be incurred 520,000 200,000 –0–Â
Customer billings to date 150,000 500,000 1,200,000
 Collection of billings to date 120,000 320,000 940,000
Instructions (a) Assuming that the percentage-of-completion method is used, (1) compute the amount of gross profit to be recognized in 2012 and 2013, and (2) prepare journal entries for 2013. (b) For 2013, show how the details related to this construction contract would be disclosed on the balance sheet and on the income statement.