The finished product requires 3 pounds of raw material and 10 hours of direct labor.
Gerrad tries to maintain a Finished Goods ending inventory equal to the next two
months of sales and a Raw Material ending inventory equal to one-half of the current
month’s production needs. January’s beginning inventories are expected to conform to
company policy.
a. Prepare a production budget for February, March, and April.
b. Prepare a forecast of the units and cost of raw material that will be required for
February, March, and April. Th e expected cost per pound of raw material is expected
to be $2 in February, $2.30 in March, and $2.40 in April.
c. Prepare a direct labor budget (assuming a $12 per hour rate) for February, March,
and April.
"
1. Prepare a Production Budget for February, March, and April; include a totals column for the period.
2. Prepare a forecast (Purchases Budget) of the units and cost of raw material that will be required for February, March, and April; include a totals column for the period.
3. Prepare a Direct Labor Budget for February, March, and April; include a totals column for the period.
4. All schedules should be in Excel and in a format appropriate for presentation to management.
Additional Requirements
Level of Detail: Show all work
Other Requirements:
-Prepare a Production Budget for February, March, and April; include a totals column for the period.
- Prepare a forecast (Purchases Budget) of the units and cost of raw material that will be required for February, March, and April; include a totals column for the period.
- Prepare a Direct Labor Budget for February, March, and April; include a totals column for the period.
- All schedules should be in Excel and in a format appropriate for presentation to management.