Subject: Business / Management QuestionQUESTION 1
The following are all a part of a coating inspection sequence Except:
Measurement of coating material quantities to be applied
Measurement of wet film thickness
Measurement of ambient conditions
Inspection of compressor equipment
QUESTION 2
When working with CML&C, an inspector should be concerned most with:
Delivery, storage and handling
Excavation and bedding
Lifting and positioning
All the above
QUESTION 3
Reviewing pipeline stationing is not a good method for an inspector to verify unit price payment for piping installed.TrueFalse
QUESTION 4
It is recommended to keep pipe trenches as narrow as practical.
True
False
QUESTION 5
It is recommended that miter-cut joints be prefabricated and inspected before being placed in position.TrueFalse
QUESTION 6
It is possible to use untreated wood Piles when the entire pile will be permanently below the water table.
TrueFalse
QUESTION 7
The following are common joint bonding problems with water stops Except:
Section misalignment
Open weld at edges
mitered joints
Vertical cut
QUESTION 8
A joint involving a _____ must be miter-cut and bonded.
tee
wye
cross
all of the above
QUESTION 9
The inspector does not have the authority to approve substitution of materials.
True
False
Multiple Choice:
QUESTION 10
The following are examples of trenchless technology Except:
Pipe jacking
Slip-Lining
HDD
None of the above
QUESTION 11
The following are all consider project close-out activities Except:
Punchlist
O&M Manuals
Record Drawings
Monthly pay application
QUESTION 12
Measure concrete slump gives the inspector an indication of the consistency of cement added to a concrete mix.TrueFalse
QUESTION 13
Minor variations in waterstop cross section should not cause field jointing problems.
TrueFalse
QUESTION 14
An inspector may possess any of the following types of authority, Except:
Actual
Apparent
Limited
All the above
QUESTION 15
Because concrete cures by hydration, it is advisable to have as much water as possible in the mix.TrueFalse
QUESTION 16
When placing concrete, higher temperatures will slow down hydrationTrueFalse
QUESTION 17
Prior to coating application, evaluation of the surface preparation equipment includes the Following Except:
Compressor air cleanliness
Blast cleaning machine
Abrasive inspection
None of the above
QUESTION 18
Compensation for thermal expansion in buried plastic pipe can be achieved by snaking the line from side to side in the trench.
TrueFalse
QUESTION 19
The following are type of pile bearing Except:
Friction piles
End bearing piles
Compaction piles
Shear bearing piles
QUESTION 20
There is no joint sawing schedule that should be ideal for every job.
TrueFalse
QUESTION 21
Sand should never be used as backfilling for pipeline installation.
TrueFalse
QUESTION 22
In inspecting dry film thickness, we take the average of _____ gauge readings.5
10
15
20
QUESTION 23
Air entrainment is used in concrete to:
Create a better surface appearance.
Increase the resistance of concrete to freeze-thaw effects.
Strengthen the concrete
Help evaporate excess water from the curing concrete.
QUESTION 24
The most common type of sheet piles is the ______ type.
Concrete
Wood
Steel
Cooper
QUESTION 25
The most important characteristic that the inspector should note about a concrete plant is the __________ of the mixes it produces.
strength
workability
grades
consistency
QUESTION 26
In a group of concrete samples, the strongest will be the one:
Cured underwater for a year
Moist-cured for 3 weeks, then allowed to air dry.
Moist-cured for 3 days, then allowed to air dry.
Cured in the air for a year.
QUESTION 27
Screeding (concrete leveling to proper elevation in the forms) takes place before consolidation.TrueFalse
QUESTION 28
Which of the following is a major concern when placing concrete:
Consolidation
Drop height
Distance moved after placed in for work.
All of the above.
QUESTION 29
Because of the reinforcement strength in concrete pipe, point load lifting and placement of pipe is not a concern for an inspector.
TrueFalse
QUESTION 30
In reinforced concrete, it is acceptable to have light rust on the surface of the steel.
TrueFalse